Software engineering practices that count

04/12/2003 14:20:29

The Scene Imagine being presented with the “opportunity” to undertake a software development project that:

• has an immutable deadline (seven months out), • is most likely under-budgeted, • possesses functionality that cannot be easily reduced, • may have serious political and reputational consequences if it fails, • must deliver a product that operates with a very high degree of integrity, and • can be cancelled at any time by the customer.

Software Improvements (SI) faced this situation when the prime contractor (Linux Care) of the successful joint bid for the Australian Capital Territory (ACT) Electoral Commission’s (EC) Electronic Voting and Vote Counting System (eVACS) became the unfortunate victim of a take-over during contract negotiations.

The subsequent SI eVACS project team that was formed used common sense software engineering decisions and practices to turn a very risky project into an unmitigated success.

The clear message I wish to convey to all other small, Australian software development companies is: Don’t go with the status quo and forsake professional practices, especially when the going gets tough!

The project in brief No detailed description of the eVACS will be provided here. However if readers are interested in knowing something about the ACT Legislative Assembly election system or specifics about the Hare-Clark proportional representation scheme that is used to count voters’ preferences, then they should refer go to the ACT Electoral Commission Web site (elections.act.gov.au). Specifics about the Hare-Clark proportional representation scheme that is used to count voters’ preferences can be found there, and a post-project report is available on the Software Improvements Web site (softimp.com.au).

The broad requirement for the eVACS project was to construct a trial system on standard PCs that could both collect and count votes electronically with no less security, no impingement of voters’ rights, and no less anonymity than is available with the current paper-based system. Internet solutions were not acceptable because of the possibility of voter coercion and system tampering.

The project was to start on March 1, 2001 and be completed by the beginning of early September 2001 for full “customer” testing and preparation for pre-poll voting that began started on September 30. Election day was October 20, 2001.

The SI team was responsible for the construction of developing software for eVACS, while InTact (the ACT Government IT provider) provided all hardware.

Why do projects succeed or fail? There is rarely just one specific reason for project success or failure; what might work well for one project may not work at all for another. Although the 1996 Standish Group (CHAOS) report of 1996 paints a sad picture of the high-end software industry at the big end of town, it is interesting to take a look at the identified reasons for both success and failure of such software development projects.

Success means within budget, on schedule and all agreed requirements are implemented and accepted by the customer. The top 10 reasons given for successful and failed projects include (in priority order):

Reasons for successReasons for failureUser involvementLack of user inputManagement supportIncomplete requirements & specificationsClear statement of requirementsChanging requirements & specificationsProper planningLack of executive supportRealistic expectationsTechnology incompetenceSmaller milestonesLack of resourcesCompetent staffUnrealistic expectationsOwnershipUnclear objectivesClear vision and objectivesUnrealistic time framesHard working and focussed staffNew technology

Do these same reasons for success or failure apply to very small projects? I think they do. On thinking about the various decisions and actions that were taken by the SI team on the eVACS project, and the reasons for them, I can see definite parallels. Fortuitous? I don’t think so. Most of the reasons for success and failure are intuitive, or common-sense, and it doesn’t require rocket science to act to prevent a reason for failure becoming a reality. However, a software development company or team cannot act confidently if their overall software engineering knowledge base within the company or team does not extend beyond coding. Continuous learning is required.

So, what decisions or actions, lead to success?

Where were we? Now that When Linux Care had dropped out of the picture, negotiations started with SI and so, the success-oriented decisions began to be made.

The following sections constitute a relatively brief synopsis of the various decisions and actions, and the reasons behind them. Each section represents a project phase describing the main decisions and actions that affected the success of the project. All except the negotiation phase were determined from the planning that occurred during negotiations.

Negotiation Decision or actionReason(s)Construct a project management plan (PMP). No proper plan existed. Some objectives were vague. Customer expectations tended to be unrealistic. Confirm project feasibility (or not). Needed to identify and treat risks. Construct a quality management plan (QMP).

eVACS had to operate with high integrity.Build a closer working relationship with customer.Discover customer’s level of ownership. Enhance the ‘team’.

The PMP and QMP together described the full scope of the system and software-related activities of the eVACS project. It was indeed feasible, even with a built built-in six-week delay caused by extended negotiations of the contract. The project life cycle was a simple waterfall model – the phases for which head up the following sections. The PMP included a basic software configuration management plan (SCMP) and a simple software change control plan (SCCP).

The deliverables included system and software requirements specifications, software design specifications, source code, acceptance tests and (of course) the fully installable system with instructions. The schedule for software delivery was based on an average estimate of 20,000 source lines of code to be developed in a ‘C’-like language. All known risks were identified. Extra specific resources were required.

Now the SI team and the customer had something with which to gauge progress.

It was during this phase that SI came to know the customer (ACT EC) better and vice versa. The commission set up a reference group, including politicians, previous electoral commissioners, typical users and a representative of the visually impaired. That group posed questions and raised issues. The Commissioner could cancel the project at any time if there was too much negative press or political backlash. Thus, the customer set the criteria for success. This input further helped to define the process for achieving a successful outcome.

System Analyses Decision or actionReason(s)Construct an eVACS system specification (SS). Requirements as stated in the Tender document had changed. Hardware components proposed in the tender response were not finalised. InTact needed to know all hardware specifications as soon as possible. identify who had ownership of what.

The SS represented an edited version of the relevant portions of the original tender document. It now contained clear system objectives, descriptions of all required hardware, and overall system functions that needed to be developed in software. It included the provision of a prototype for the voting and counting parts of the system.

At least now all parties involved in constructing eVACS were clear now on overall system requirements. Some ownership was beginning to occur.

Software Analyses Decision or actionReason(s)Nail down software requirements.Some requirements were vague. Requirements didn’t seem complete. The customer had not sanctioned fully the proposals in the tender response. Setting and confirming expectations. Construct an eVACS software specification in the form of a model. Capture requirements more formally. A model provides an easy way to identify the affects of proposed changes easily. Identify separation of concerns within the model.Smaller project milestones. Less time between deliveries. Provide a prototype.Show customer and users the nature of computer interfaces. Obtain user involvement.

It was no surprise to hear the customer expressed great pleasure and relief when approached by Software Improvements to discuss the requirements. A full scenario analysis was performed by identifying required actions of the system as produced by expected stimuli (events). The customer had no trouble at all with the concept. In addition to identifying event/action pairs, system state at the time of the event, and any necessary action data were also identified. Stick figures and named ovals were not used. Sorry Ivar!

The scenario document had begun with analyses of the tender and tender response, producing a nine-page table containing 41 requirements. After two days with the customer this document expanded into a 39-page table containing 79 requirements.

The benefits were obvious. The software functionality was now fully scoped and therefore a better estimate of required effort could be made. Acceptance tests could now be easily constructed. The customer now realised the extent of the work being undertaken by the SI team and thus some prioritisation of requirements was quite acceptable.

The requirements were modelled using a real-time structured analysis approach, in line with the eVACS being an event and process-driven system.

The model provided a clear picture of the operational scope of eVACS as well as clear definitions of data input and output. Areas of reuse and also areas where functionality could be reduced without ill affect were easily identified. For example, there was obvious reuse of functionality between the voting part of the system and the paper vote data entry part of the system. Also, a clear reduction in functionality within the data entry part of the system was gained by reducing the size of paper vote batches from 500 down to 50.

Acceptance testing was enhanced with the model because data input and output ranges were well defined.

The modelling proceeded incrementally with separation of the system into four components: Election Set-up, Voting, Data Entry, and Counting. Each of the component models was incorporated into separate software requirements specifications (SRS). The final combined set of four SRS documents consisted of 158 pages, including 34 data flow and/or state transition diagrams, written process specifications, an extensive data dictionary and a requirements traceability matrix.

The model provided the basis for a more accurate estimate of size and effort. The new estimate of size didn’t vary much from the previous one, but the effort estimate was lower.

The SRS documentation provided all that was necessary to construct a design.

Software Design Decision or actionReason(s)Construct architectural design of software.Allow planning of coding effort. Provide a visualisation of the structure of the software to all parties. Focus the planning and implementation of integration and system testing. Provide detailed design specification. Give hired programmers an easy way to understand what they are required to do. Form basis for unit tests.

The design came together relatively quickly, mainly because the team had worked closely together and captured a very similar visualisation and understanding of the system.

The identified reductions in functionality and areas for reuse (mentioned earlier) were included in the design so that programmers were not duplicating effort.

Each design module was specified using a standard format in pseudo-code with pre- and post-conditions described wherever possible. Thus a programmer who had to code up the module was presented with a contract for coding and testing.

The hired programmers (one of whom was very experienced) could not believe that they could be productive within four hours of joining the SI team.

The architectural part of the software design document (SDD) contained 31 pages including 10 module specifications, whilst the detailed part of the document (SDDD) contained 306 pages including 47 diagrams and around 327 module specifications.

Software Coding

Decision or actionReason(s)Code according to SDD and SDDD specifications.The design describes how the requirements should be implemented. The design is also the plan for building the code. Perform code reviews and inspections. Ensure consistent coding practices. Sharing of knowledge and issues.

The main coding and testing effort took seven weeks of elapsed time. Less than planned. Review meetings were held every other day and were intensive sessions to ensure that everyone was progressing, cooperating, and sharing problems and solutions. Each coder was aware of each other coder’s productivity and so work was distributed accordingly.

The code was audited, both before and after the election, for possible insecurities and any hidden attempts to alter the outcome of the election. The auditor found no insecurities or hidden schemes but (before the election) did expose nine faults. Five were regarded as serious enough to possibly cause instabilities, but otherwise would not affect the outcome of the election result. Four faults were regarded as minor or cosmetic.

Toward the completion of the coding phase the customer informed the team that the facility for the sight-impaired ‘had to be’ included. The team had not included the facility to date because there had not been enough time.. However it became a political must. To cut a long story short, the team and the customer together implemented the sight-impaired facility. If there were no ownership on the part of both parties then the cooperative effort would not have occurred.

There were 21,810 non-blank, non-comment source lines of ‘C’ code in the final eVACS. The source was distributed among 182 “.c” files together with 80 “.h” files.

Software Testing Decision or actionReason(s)Write acceptance test cases & and procedures for the customer in accordance with the SRS.The tight schedule. Ill-conceived tests from the customer. Shared ownership and expectation.

The well-structured design meant that unit and integration tests could be written, in accordance with the design, as the coding progressed. The customer reviewed the acceptance tests (some of which were quite complex) and any errors were corrected.

The human side of the project Most of the SI team possessed information technology, computer science or software engineering qualifications together with several years experience. They all possessed strengths and weaknesses in their profession and these were acknowledged and accepted by all. The team was truly a group of professionals and without their wise planning and decision making the project would almost certainly have failed.

A true test of the professional nature of the team was had with several very unfortunate and one tragic episode during the course of the project. The project lead’s life-partner was hospitalised for several weeks with an unknown liver disorder and the diagnosis was fatalistic. The wife of another major member of the team fell in a car park and splintered both elbows, making it virtually impossible for her to hold and feed their young child of five months. The elderly mother of the quality assurance manager died and he had to go to the UK to make funeral arrangements and arrange for his elderly father to be put into proper care. Another SI employee with three young children lost her husband in tragic circumstances. My own mother died of cancer on September 11. Through all this the team remained a team.

Epilogue The elapsed time of the project was 135 working days containing an overall effort of 334 person days. The hardest-worked SI employee averaged 45 hours per week during the project period. Contracted people were typically hired for a maximum number of hours within a defined period and very rarely did more than an eight-hour day.

The effort distribution over the project was as follows:

11 per cent - prototype. 27 per cent - requirements (scenario analysis, modelling and design). 38 per cent - coding, unit, integration and system testing. 24 per cent - acceptance testing and deployment.

The implemented eVACS did what it was required to do at the October 2001 ACT Legislative Assembly elections. By the time the full count had been completed the ACT EC had proved that counting by hand was too inaccurate, especially for close-run results – as occurred in this election.

No voter who used the system complained, even when the barcodes used to start and finish a voting session sometimes had to be swiped many times before the barcode reader accepted the input. Voters often went out of their way to vote electronically and then often had to line up in long queues.

Since project completion the ACT EC has promoted both eVACS and Software Improvements several times. They have also contracted SI to undertake modifications to the eVACS.

eVACS went slightly over-budget, but SI does have the IP.

Conclusion How you address the common reasons for success and failure (as reported by the Standish Group) seems very important. It’s not appropriate to be aware of these various reasons and then use ill-thought-out actions to try and support success or counteract failure. Software development companies and teams need to possess software engineering knowledge and capability.

If the team cannot put a plan together, and/or doesn’t understand how to clarify or elicit requirements, and/or doesn’t know how to construct models or designs, and/or doesn’t know how to plan and construct tests, and/or doesn’t know how to manage a project then they are not going to be able to make reasonable decisions that positively promote success.

The ACT EC has received a well defined, well documented, tested, and maintainable system. I’d hate to think what might have been produced if the SI team had undertaken the usual panic approach of “code, code, code for there isn’t enough time to do that other stuff”.

In addition to the Standish Group of listed reasons for success, I believe that the following are also very important:

Make sure that the customer’s objectives are always being met. Form a close professional, relationship with the customer. Make sure the team is a team. Construct clear specifications at every phase of the project.

Dr Clive Boughton is director of Software Improvements. He has been offering software engineering training and consulting for the last 10 years, and is on the staff of ANU. He has also been involved in industrial and defence applications of software engineering for 15 years.